Sustainable long-term solutions

There is a commitment to address the reflectivity of the facade by over-cladding the reflective elements with a textured metal that is visually comparable to the current finish but will reduce the reflectivity.

A detailed construction methodology has been worked through to ensure all aspects of the installation are properly considered in relation to safety and the overall installation process.

In order to minimise the disruption to the public realm during the overhead works, the Market Street tower and William Street tower have been sequentially programmed (that is, each tower is to be completed separately), with a minor overlap during the last stages of the Market Street tower works.

Permanent works to address the reflectivity of the facade will commence in Q4 2022 and are anticipated to be completed in Q3 2024 (Market Street tower) and Q4 2025 (William Street tower).