Upcoming works - December 2024 / January 2025

19 December 2024

William Street tower

  • Facade works will pause during the construction shutdown period from 19 December 2024 to 14 January 2025.
  • Over-clad installation on the William Street facade will resume after the shutdown period.
  • Over-clad installation on the Collins Street facade is now complete, with mast climber removal works now underway.
  • Subject to weather and progress, the Collins Street mast climbers are expected to be fully removed in Q1 2025.
  • 2025 works will be conducted from Monday to Saturday, from 7am to 5pm (excluding public holidays and construction lockdown weekends / rostered days off).
  • Traffic management will continue to facilitate material deliveries for the completion of works.

*All above-mentioned works are subject to inclement weather. All working hours referenced are in accordance with City of Melbourne requirements.

*For traffic and pedestrian safety, signage and traffic controllers will be in place during any temporary footpath and/or road closures required for the above-mentioned works.